Just the one picture today.  It's been a little while since my last inside visit, and work is progressing at a great rate of knots. 
No more so, than on the pitch.  I've post a lot of images today, so the text for each one, is underneath picture.

A panorama view, from the top of the West stand.  As you can see, all drainage is complete, and the underground
 heating pipes are being laid.  All 27 miles of it !!

This picture is taken from the North stand, looking down the length of the pitch

Looking from the South stand, towards the North stand.  It's at this end that all the pipes
get connected together

Again, looking from the South stand, more pipes are delivered
for installation.  As you can see, there's not much left to do.

This picture was taken at the North stand end.  The pipes are
sitting on the top of the shingle, and covered in sand

This is how the pipes are kept evenly spaced

Here are all the pipes at the end of the South stand

Taken from the North stand, the pipe in the bottom right hand
corner, is one of the holes for the goal post, the stick (just under
the blue cherry picker) is the centre of the goal


The washrooms are starting to be fitted out too.

A very rare event, a view, from the top of the roof !  The Xscape can be seen in the distance

The roof has nearly been completed on the Ballroom.

Cladding has started to commence on the Ballroom

Lots more cladding to be fitted yet

Pilings and foundations for
the Event Arena are well in hand.  This trench is
the length of the new Arena. The columns you see
were placed by the pile driver that left site earlier
this week.  "Rebar" will be placed in the trench,
followed by concrete.  At this point, steelwork
will start.


Just a very quick view of the swimming pool